Observations of a Sidewalk Supervisor  : - )

Power was shut down on Monday, October 30 at 8:40 a.m. and restored Tuesday, October 31 at 3:40 p.m.  Other than a few minor glitches all went well.  The "green tag" was received from the city inspector around noon.

Meanwhile on the other side of the building, two crews from High Tech have been working under the threat of a storm forecast for late night October 31.  They made good progress on the 14 foot forms and rebar that have to be installed.   

 