We have forms! We have concrete poured!
We have some visible construction! Check out Week Five above. There
are more pictures than what can fit in our web space. Workers were
blessed with a beautiful day and other than an erratic behaving pumper
tube, the pouring of footers seemed to go well. Wall forms went up on
Wednesday. There is a great deal of clamoring in the basement as the
electrical crew prepares for the big power switch which is scheduled to
occur Monday. The church will be without power on Monday, October
30 and possibly on the 31.
|