The guys from High Tech and DRM worked hard to beat the weather forecast, and they did it!  The deck is on the Fellowship Fall and the entire Fellowship Hall is back-filled.  More than that, DRM was able to completely excavate for the Office / Youth Room.  The smaller dirt pile remaining on the parking lot will be removed next week.
To the left is Roger Mortensen.  Trinity owes accolades of thanks to Roger.  He is our treasurer.  Roger is thorough.  Roger pays bills on time.  Roger has done a marvelous job for this congregation. 

Thanks Roger!

Excavation got underway for the east side of the building.  This will be for the new Youth Room (basement) and the additional office space.
DRM also began backfilling the Fellowship Hall, while the High Tech crew is putting the deck on the top of the joist.

The sinks are taken out of the kitchen (below).

 

Walls for classrooms will be put up yet this week in the basement. 

 