The problem encountered at the end of last week has spilled into this
week. Those in charge vacillated between seeking to shore up the
vent chase on the north side of the building and tearing it down.
Both options involved a change order. It was agreed to proceed with
demolition. Demolition was accomplished October 10-13. LCEF approval for the change order came through at noon on
October 10. Another change order was handled at the same time in that the city placed the transformer for the building closer to the street than what had been anticipated. This means that a switch must be installed and that route of the electrical line to the building must be changed. Forms were delivered this week. Blair electric has brought their trailer to the site. |
||