Week 32:  April 30 - May 4, 2001

Plenty of "things" interfered with production of the website this week - mostly the Wyoming District Pastor's Conference in Alliance, Nebraska.  

The jobsite progress was also hampered by a mix up with scheduling the Ironworkers.  It was our understanding that they were going to be on site putting up steel for the Narthex edition this week.  From what we know at this time, they will be here Monday, May 7.

Pictured left is Larry of Hi-Tech who installed all of the wooden doors in the basement, as well as the outside doors on the Fellowship Hall, Youth Room and Office building.  Hi-Tech workers also raised the soffit in the Fellowship Hall.  Brick workers started closing in the door entry of the Office Building.  We anticipate weld and bolt inspections on Friday.